A Server with 8 H200s Costs 100 Million Rubles and 1.67 Million a Month: How to Split the Bill Across Teams

A server with eight Nvidia H200 GPUs costs 100 million rubles. Amortized over five years, that comes to 1.67 million rubles a month, even when the machine sits idle. There are three ways to divide the bill among teams: fixed allocations, a per-hour GPU rate, and separate accounting for GPUs, memory, and CPU cores. At 54% utilization against plan, idle costs are split by consumption, and the totals add up to zero. The right method depends on how evenly teams draw on resources.

AI-processed from Habr AI; edited by Hamidun News
A Server with 8 H200s Costs 100 Million Rubles and 1.67 Million a Month: How to Split the Bill Across Teams
Source: Habr AI. Collage: Hamidun News.
Listen to article
Article Fact Sheet & Key Figures
ParameterDetails
Primary sourceHabr AI ↗
Editor-in-Chief
Key metric #1Hourly cost of one H200 at an 80% utilization target: 361.69 rubles
Key metric #2Idle cost of 762,442 rubles is split across teams by their GPU-hours
Key metric #3A team that takes 80% of RAM per GPU pays for the lock itself

Imagine a company buys one server for AI projects for 100 million rubles, and several teams use it. One runs model training, another handles inference, and a third has forgotten about its quota entirely. The hardware bill arrives the same either way, whether the machine is busy or not. Dmitry, head of IT infrastructure at Vi.Tech (the IT subsidiary of VseInstrumenty.ru), worked through the numbers on how to split such a bill between profit centers and cost centers (PnL centers) so that no one is left holding the bag. This is the fifth part of his series on FinOps, the management of IT spending.

Where the 1.67 million rubles a month comes from

In the example, the server costs 100 million rubles. It has eight Nvidia H200 GPUs (AI accelerators), 3 TB of RAM, and 128 CPU cores. Depreciation runs over five years, or 60 months, so dividing 100 million by 60 gives roughly 1.67 million rubles a month. For simplicity, the author counts only the server's purchase price. In practice, data center space, electricity, licenses, and engineer salaries would need to be added.

The first approach is fixed allocation. The cost is divided by component: GPUs take 70% (70 million), memory 20%, and CPUs 10%. That works out to about 145,834 rubles a month per GPU, 109 rubles per GB of RAM, and 1,302 rubles per core. Each team gets a set of resources and receives an invoice. The approach is transparent but wasteful. If a team doesn't load its GPU, that GPU sits idle and never pays for itself. And if another team occupies capacity for a long stretch, the rest are short on resources.

Paying for GPU-hours

The second approach folds the cost of CPU, RAM, and disks into the price of GPU time. The GPU accounts for 70–80% of the server price, and the rest is treated as supporting infrastructure. Resources are not assigned permanently to teams. They are drawn on demand and billed by the hour, or even by the minute.

For the calculation, the author uses an 80% utilization target. Instead of 720 hours a month, that leaves 576, since some time goes to incidents and maintenance. Across eight GPUs, that is 4,608 GPU-hours, and one GPU-hour costs about 361.69 rubles. Consumption data is collected with the NVIDIA DCGM Exporter.

In an ideal month, the first team uses 1,500 hours (542,535 rubles) and the second uses 3,108 hours (1,124,132 rubles), and the total equals 1,666,667 rubles. That rarely happens in practice. Suppose the teams logged 1,000 and 1,500 hours. Then utilization reached 54.25% of target, and only 904,225 rubles is covered. The remaining 762,442 rubles is the cost of idle time. It can either be written off to the IT department or split across teams in proportion to consumption, in this case 40% and 60%: about 305 thousand and 457 thousand rubles. The final invoices come to roughly 667 thousand and 1 million rubles, and the sum adds up again.

This method works well when an orchestrator slices containers and virtual machines in proportion to GPUs: each GPU maps to 16 cores and 384 GB of memory. If teams draw CPU and RAM unevenly, the model breaks down.

Separate accounting for GPUs, memory, and cores

Suppose one team takes just a single GPU but requests 80% of the server's memory for a huge dataset. The others cannot start, even though the GPUs are free. For cases like this, the author proposes a third approach. The monthly 1.67 million rubles is split into GPU, RAM, and CPU pools in a 70/20/10 ratio, and the hourly rate of each resource is calculated over 720 hours a month:

  • GPU: about 202.55 rubles per hour;
  • RAM: about 0.15 rubles per GB per hour;
  • CPU: about 1.81 rubles per core per hour.

The first team ran for 500 hours on 32 CPUs, 1,024 GB of RAM, and 2 GPUs, and is charged about 308 thousand rubles. The second ran for 600 hours on 32 CPUs, 1,536 GB of RAM, and 4 GPUs, which comes to about 659 thousand. The undistributed 699,245 rubles is split by weight, meaning each team's share of the costs already charged. The total adds up to 1,666,667 rubles.

The upside of this approach is flexibility: configurations are not fixed, and idle time caused by a team that monopolizes memory is paid for by that team. The downside is complexity, since metrics must be collected for three resource types.

What to do in practice

The author stresses that all three methods work, and the choice depends on the scenario. If there are few teams and resources are cut into even chunks, fixed quotas are enough. If there is an orchestrator and proportional configurations, per-hour GPU billing fits. If workloads are heterogeneous, separate accounting is needed. In every case, decide in advance who pays for idle time: the IT department or the teams themselves. Otherwise, expensive H200s will sit idle with no one accountable for them.

Story

Key Questions Answered

Where the 1.67 million rubles a month comes from?

In the example, the server costs 100 million rubles. It has eight Nvidia H200 GPUs (AI accelerators), 3 TB of RAM, and 128 CPU cores. Depreciation runs over five years, or 60 months, so dividing 100 million by 60 gives roughly 1.67 million rubles a month. For simplicity, the author counts only the server's purchase price. In practice, data center space, electricity, licenses, and engineer salaries would need to be added. The first approach is fixed allocation.

What are the key details on Paying for GPU-hours?

The second approach folds the cost of CPU, RAM, and disks into the price of GPU time. The GPU accounts for 70–80% of the server price, and the rest is treated as supporting infrastructure. Resources are not assigned permanently to teams. They are drawn on demand and billed by the hour, or even by the minute. For the calculation, the author uses an 80% utilization target. Instead of 720 hours a month, that leaves 576, since some time goes to incidents and maintenance.

What are the key details on Separate accounting for GPUs, memory, and cores?

Suppose one team takes just a single GPU but requests 80% of the server's memory for a huge dataset. The others cannot start, even though the GPUs are free. For cases like this, the author proposes a third approach. The monthly 1.67 million rubles is split into GPU, RAM, and CPU pools in a 70/20/10 ratio, and the hourly rate of each resource is calculated over 720 hours a month: GPU: about 202.55 rubles per hour; RAM: about 0.15 rubles per GB per hour; CPU: about 1.81 rubles per core per hour.

ZK
Zhemal Khamidun — CPO at Alpina Digital, product manager of AlpinaGPT. Building AI products since 2019. Hamidun News is a pet project that grew into a production aggregator with 6,000+ readers.
✦ Unified AI Workspace · Nomad

Test Frontier LLMs & Autonomous Agents in One Workspace

Run Claude Opus 5.5, GPT-6, Gemini 3.1, and DeepSeek side-by-side in Nomad AI (nomadnet.ai) — unified model routing, deep research, and multimodal workflows under one subscription.

Try Nomad AI →Launch Nomad Agent
What do you think?
Loading comments…