ReleaseInsight · On RadarMIT Technology Review→ original

Data Centers Bypass the Grid: 115 GW of Gas Plants Announced, 4.9 GW Operating

Connecting a new AI data center to the US grid can take up to ten years, so developers are putting their own gas plants next to the buildings. More than 100 projects totaling 115 GW have been announced (1 GW is one million kilowatts), which is more than twice California's peak load, but only 4.9 GW is operating. Running on your own gas costs more than grid power, but it gets you online faster. For AI infrastructure, speed matters more than the price of energy.

AI-processed from MIT Technology Review; edited by Hamidun News
Data Centers Bypass the Grid: 115 GW of Gas Plants Announced, 4.9 GW Operating
Source: MIT Technology Review. Collage: Hamidun News.
Listen to article
Article Fact Sheet & Key Figures
ParameterDetails
Primary sourceMIT Technology Review ↗
Editor-in-Chief
BloombergNEFby 2035, these plants would emit 345 million tons of CO₂ per year
Key metric #2That is 152 million tons more than if the same data centers were powered from the grid
Key metric #315.8 GW is under construction, and most of the plants are not combined-cycle

Imagine you have bought thousands of GPUs and built a facility for an AI cluster, but there is no electricity for it: the grid operator says the connection will take years, sometimes up to ten. That is the situation US data center developers now face. Some of them are no longer waiting and are installing their own gas power plants on site.

The approach is called "behind the meter": the plant sits on the customer's side and powers the building directly, bypassing the grid. According to the analytics firm Cleanview, as of October 2026, more than 100 such plants with a combined capacity of over 115 gigawatts have been announced (1 gigawatt is one million kilowatts). For scale, that is more than twice California's peak electricity consumption.

But only 4.9 GW is operating so far.

How many projects are actually running

This used to be rare. xAI's campus in Memphis was already running on dozens of gas turbines in 2024, some of them without permits, and it is still in litigation with regulators. Now many companies do the same: almost all of the announcements have appeared since early 2025.

An important caveat: most of these projects still exist only on paper. Besides the 4.9 GW of operating plants, another 15.8 GW is under construction, and the rest is planned. BloombergNEF takes a broader view: 181 GW of projects announced worldwide, 90% of them in the US.

Why companies pay more to move faster

An on-site plant usually costs more than a grid connection. But, as BloombergNEF analyst Musfika Mishi says, the main motive right now is speed. Grid connection is a years-long process: the operator studies what must be built to deliver power safely, such as new lines and larger transformers, and some of those costs may fall on the developer. A gas plant lets developers skip the queue.

Many see it as a bridge. Brendan Pierpont of the think tank Energy Innovation calls it "a very expensive way to cover a five-to-seven-year gap" until a grid connection arrives. After that, the plant stays on as backup. The risk is that an owner who has already invested will keep using it. Mishi calls this fossil fuel lock-in.

Climate and ordinary people's bills

Because manufacturers are short on equipment, many developers are turning to less efficient turbines. Large utility gas plants usually run in combined-cycle mode: the turbines use exhaust heat to generate additional electricity. Simple-cycle turbines are cheaper to build but less efficient. Mishi says only a few of the planned off-grid plants will be combined-cycle. That means more emissions per unit of energy than conventional gas generation.

BloombergNEF's calculations: if all planned plants in the US are built, by 2035 they would emit 345 million tons of CO₂-equivalent per year. That is 152 million tons more than if the same data centers were powered from the grid, and more than the annual emissions of the entire Netherlands. The reason is simple: in the US, nuclear and renewables together generate about 40% of electricity. In countries like India, where the grid is largely coal-based, the outcome could be different.

There is also a hit to wallets. Matthias Fripp of Energy Innovation explains that off-grid plants do not protect others from rising prices. Additional demand for gas can push its price up, and that affects the roughly 60% of American households that use gas for heating and cooking, and indirectly electricity rates.

What could be done differently

Hybrids could soften the impact: a gas plant combined with on-site solar and storage would run less often, although the economics of such a setup are difficult. In a recent study, Fripp's team concluded that renewables with storage can reliably cover growing demand and cost less than fossil fuels.

For developers and founders, the takeaway is practical. The cost and timelines of AI infrastructure are increasingly determined by energy, not just chip purchases. The planned 115 GW is more of a claim than a fact: less than 5 GW is actually running. But if the trend holds, it will shape the power system and the climate for decades. Fripp puts it bluntly: leaving the grid and building your own gas is likely a bad path, because it will still raise other people's bills and harm the environment.

Story

Key Questions Answered

How many projects are actually running?

This used to be rare. xAI's campus in Memphis was already running on dozens of gas turbines in 2024, some of them without permits, and it is still in litigation with regulators. Now many companies do the same: almost all of the announcements have appeared since early 2025. An important caveat: most of these projects still exist only on paper. Besides the 4.9 GW of operating plants, another 15.8 GW is under construction, and the rest is planned.

Why companies pay more to move faster?

An on-site plant usually costs more than a grid connection. But, as BloombergNEF analyst Musfika Mishi says, the main motive right now is speed. Grid connection is a years-long process: the operator studies what must be built to deliver power safely, such as new lines and larger transformers, and some of those costs may fall on the developer. A gas plant lets developers skip the queue. Many see it as a bridge.

What are the key details on Climate and ordinary people's bills?

Because manufacturers are short on equipment, many developers are turning to less efficient turbines. Large utility gas plants usually run in combined-cycle mode: the turbines use exhaust heat to generate additional electricity. Simple-cycle turbines are cheaper to build but less efficient. Mishi says only a few of the planned off-grid plants will be combined-cycle. That means more emissions per unit of energy than conventional gas generation.

ZK
Zhemal Khamidun — CPO at Alpina Digital, product manager of AlpinaGPT. Building AI products since 2019. Hamidun News is a pet project that grew into a production aggregator with 6,000+ readers.
✦ Private AI Builders Community · Vibe Club

Ship AI Faster with Founders, Engineers & Weekly Architecture Reviews

Inside Vibe Club (hamidun.com/club) — weekly live masterminds with Zhemal Khamidun, Tech Radar, full LMS access, and 370+ production Claude Code skills.

Join Vibe Club →Explore Hamidun Academy
What do you think?
Loading comments…