Nebius Shares Fall 16% on Data Center Delays Despite 571% Revenue Growth
Shares of cloud AI provider Nebius fell 16%, even though third-quarter revenue rose 571% year over year to $980.8 million. Investors were rattled by delays: some of the data centers it leases won't be ready in 2026, so full-year revenue is expected at the low end of the $3–3.4 billion range. It's like a store with a line of customers whose building was never connected to the power grid. For that reason, providers' GPU delivery timelines are best planned with a buffer.
AI-processed from TNW; edited by Hamidun News
Picture a store with a queue of customers already lined up, but the building it rents hasn't been connected to electricity yet. That is roughly what happened to Nebius, an Amsterdam-based cloud provider that rents out capacity with graphics cards (GPUs) for training and running AI models. On Thursday its shares fell 16%, even though third-quarter revenue rose 571% from the same quarter a year earlier to $980.8 million. Growth beat expectations, but the company cut its 2026 forecast: some data centers it leases from other owners will come online later. For developers and founders counting on available GPUs, this is a reality check: the shortage is driven not by demand but by concrete and electricity.
What the results showed
Analysts polled by LSEG expected $907.5 million for the quarter, so Nebius beat the forecast. Adjusted EBITDA (earnings before interest, taxes, depreciation and amortization) came in at $465.8 million, compared with a loss of $5.2 million a year earlier. The net loss narrowed from $119.6 million to $37.5 million.
The forecast unsettled investors. Nebius now expects 2026 revenue at the low end of the $3–3.4 billion range, while analysts had expected $3.37 billion. At the same time, the company raised its capital expenditure plan for this year to roughly $27 billion, up from the earlier $20–25 billion. Revenue is shifting down while spending climbs, and the market reacted to exactly that.
Why the timelines slipped
The cause is not lost customers. Some of the capacity Nebius leases in other companies' data centers won't be commissioned this year, and it has moved into the first half of 2027. The contracts remain in force. One of these sites, a 300 MW facility in Vineland, New Jersey, is held up by its power connection. Major customers there include Microsoft.
Founder and CEO Arkady Volozh acknowledged the problem directly: building at this scale is hard, the entire industry is facing delays, and Nebius is no exception. He said customers were warned, and the capacity has not been cancelled. According to him, the company's own sites are on schedule or ahead of it, and most of the next gigawatt will be brought online there rather than on leased facilities.
A everyday analogy: you ordered powerful machines, customers are waiting in line, but the leased workshop was never hooked up to the grid. The money isn't lost, but it will arrive later, while the costs are being incurred now.
Money for 2027
The plan for next year is even more aggressive. Nebius intends to spend $40–45 billion, while analysts polled by FactSet had expected $28.77 billion. The company forecasts 2027 revenue of $12–13 billion and expects to reach pre-tax breakeven by the end of 2027.
Customer prepayments and asset-backed financing are expected to cover 75–85% of the spending. That financing rests on existing contracts with major customers, including Microsoft and Meta. Chief Financial Officer Dado Alonso said there is no doubt about selling this capacity: customers are already looking for capacity for 2028, and prices for 2027 are rising.
Context and limitations
The decline fits a broader market nervousness. In October Nebius had already lost more than a third of its value, as investors question whether multibillion-dollar bets on AI infrastructure will pay off. Rival CoreWeave reported better-than-expected results on Tuesday. Nvidia is among Nebius's shareholders: at the end of June its stake was valued at roughly $329 million.
The 2027 projections are the company's own statements, and the enormous spending plan depends on the availability of borrowed money and on sites being commissioned on time. If power and construction delays recur, not only revenue quarters but also financing conditions could shift.
What practitioners should do
Teams planning training or inference on cloud GPUs should build a schedule buffer: a provider's promised capacity date can slip by six months even when a contract is signed. Product managers would do well to plan a multi-cloud setup and backup suppliers in advance. As for demand, Volozh says it is not in doubt: "Everything else, the construction of capacity and its financing, is just a task."
- Nov 21, 2026Applied Digital Asks Oracle and Meta for Billions in Power Guarantees
- Nov 21, 2026Meta may sell Muse Charm, a pocket AI pet, for $300
- Nov 21, 2026Meta's Muse AI Agent Read Signal Chats and Made Up Purchases — It Has Been Downloaded 10 Million Times
- Nov 21, 2026California Sues OpenAI: 700 of Its AI Agents Spent a Week Attacking Hugging Face
Key Questions Answered
What the results showed?
Analysts polled by LSEG expected $907.5 million for the quarter, so Nebius beat the forecast. Adjusted EBITDA (earnings before interest, taxes, depreciation and amortization) came in at $465.8 million, compared with a loss of $5.2 million a year earlier. The net loss narrowed from $119.6 million to $37.5 million. The forecast unsettled investors. Nebius now expects 2026 revenue at the low end of the $3–3.4 billion range, while analysts had expected $3.37 billion.
Why the timelines slipped?
The cause is not lost customers. Some of the capacity Nebius leases in other companies' data centers won't be commissioned this year, and it has moved into the first half of 2027. The contracts remain in force. One of these sites, a 300 MW facility in Vineland, New Jersey, is held up by its power connection. Major customers there include Microsoft. Founder and CEO Arkady Volozh acknowledged the problem directly: building at this scale is hard, the entire industry is facing delays, and Nebius is no exception.
What are the key details on Money for 2027?
The plan for next year is even more aggressive. Nebius intends to spend $40–45 billion, while analysts polled by FactSet had expected $28.77 billion. The company forecasts 2027 revenue of $12–13 billion and expects to reach pre-tax breakeven by the end of 2027. Customer prepayments and asset-backed financing are expected to cover 75–85% of the spending. That financing rests on existing contracts with major customers, including Microsoft and Meta.
Test Frontier LLMs & Autonomous Agents in One Workspace
Run Claude Opus 5.5, GPT-6, Gemini 3.1, and DeepSeek side-by-side in Nomad AI (nomadnet.ai) — unified model routing, deep research, and multimodal workflows under one subscription.
The AI world, distilled — once a week
Seven stories that actually mattered, hand-picked. No noise, no reposts, no press releases.
Done! Check your inbox for a confirmation.