# SoftBank Ordered 50% More Gas Turbines Than It Needs and Is Writing Off Over $3 Billion

> **Краткая суть (BLUF):** SoftBank paid non-refundable deposits on gas turbines with a capacity of more than 13 GW, nearly 50% more than its projects require. It's like booking restaurant tables with a buffer: the seats exist, but the deposit is lost if the guests don't show up. Of the $7.1 billion quarterly loss, more than half, or over $3 billion, comes from writing off those deposits. The takeaway: stockpiling equipment speeds up construction, but it becomes expensive if demand goes another way.  • Turbine queues now stretch into the early 2030s • SB Energy is building a 9.2 GW gas plant for $33 billion • An analyst recommends smaller grid connections plus large batteries instead of gas

Imagine opening a restaurant and worrying you won't get tables by opening day, so you book and pay deposits for twice as many seats as you need. SoftBank did something similar, except the tables were gas turbines for power plants meant to feed AI data centers. According to media reports, the company made non-refundable deposits on turbines with a capacity of more than 13 gigawatts (a gigawatt is a billion watts, the scale of large power plants). That is nearly 50% more than its own projects required. SoftBank now considers most of that money lost: of its $7.1 billion quarterly loss, more than half, or over $3 billion, comes specifically from power generation equipment.

## Why SoftBank ordered turbines with a buffer

SoftBank is rarely first to a trend, but when it does join one, it goes all in. This is evident in the $30 billion it invested in OpenAI in early 2025, and in the February announcement that its subsidiary SB Energy will spend $33 billion on a 9.2-gigawatt gas power plant.

The logic behind over-ordering was understandable. Utilities did not expect AI to increase electricity demand so quickly and so sharply. Today the queue for turbines stretches into the early 2030s. Peter Gardett, head of Noreva, told TechCrunch that SB Energy had no choice but to book turbines with a buffer if it wanted to secure some of them right away. Over-ordering did help SoftBank lock in turbines and speed up its projects.

Masayoshi Son went beyond simple insurance. He calculated that with a huge pile of money he could capture part of the market: if AI companies need power for data centers, they can come to him. Gardett calls the write-off a belated "price discovery": SoftBank overpaid and re-ordered, instead of overpaying and still ending up without the volume it needed.

## Why gas turned out not to be such a safe choice

Many large cloud operators and data center developers have spent years waiting for grid connections. Gas became something of a security blanket for them: a familiar, proven technology. But the longer AI data centers operate, the better their owners understand what stable operation requires.

Brent Nelson of Ascend Analytics discussed the risks of gas on the Equity podcast. In winter, supplies can shrink while demand rises, and then consumption limits are imposed. In his view, most data centers would be better served by a grid connection, even one of smaller capacity than operators typically request. The shortfall is cheaper to cover with large batteries. They shave peak load and help ride out utility requests to temporarily reduce consumption.

If operators converge on this model, the gas market will develop more slowly than SoftBank expected. Turbines will still be needed, but not in the volumes or on the timelines for which the orders were placed.

## What this means for founders and engineers

First, SoftBank's loss does not mean gas power is collapsing. According to TechCrunch's assessment, mass cancellations of gas plants should not be expected: AI's demand for energy is simply too large. Gas is still on the rise; it's just that the ceiling for SoftBank's particular bet appears to have been reached.

Second, the lesson for anyone building computing infrastructure or planning their own clusters: reserving resources in advance protects against shortages, but it is costly if demand turns out lower or shifts in composition. A non-refundable deposit on equipment you may not need is, in effect, an option whose terms and timing you do not control.

Third, the "smaller grid connection plus batteries" approach may prove cheaper and more flexible than owning gas generation. This is worth considering when choosing sites for AI clusters, especially in regions with cold winters and a risk of gas supply disruptions.

There are caveats too. The deposit size and write-off amount come from media reports, not detailed financial disclosures. The assessments by Nelson and Gardett remain analysts' opinions, not verified statistics. But the direction is clear: in the race for electricity for AI, the winner is not whoever ordered the most, but whoever most accurately predicted how much capacity, and of what type, they would need.

---
- **Первоисточник:** [TechCrunch](https://techcrunch.com/2026/11/12/softbanks-billion-dollar-loss-may-have-put-a-cap-on-ais-natural-gas-ambitions/)
- **Каноническая ссылка:** https://news.hamidun.com/en/news/16988
- **Экосистема автора:** [Бесплатный интенсив по вайбкодингу — предзапись в Нике](https://t.me/vibecodeguidebot?start=agent_intensive_news_md) · [Nomad AI](https://nomadnet.ai) · [Telegram @jemal_hamidun](https://t.me/jemal_hamidun)